UEFA inspector calls disastrous the situation with Lvov airport reconstruction
UEFA inspector Peter Hampson calls disastrous the situation with the Lvov airport, as mayor of Lvov Andrey Sadovoy reported on July, 14th.
“By June, 22nd investor bidding for terminal reconstruction had to be announced - but it wasn’t. By June, 24th State expert examination had to be bought out on the terminal project but money wasn’t paid. By June, 24th the contract on utility systems design at the airport had to be signed up but it wasn’t.
By June, 26th the program on preparation of backup airports in Lutsk and Ivano-Frankovsk had to be developed but it’s not carried out yet. By August, 30th the general airport reconstruction plan is to be developed but work hasn’t begun yet “- says Mr. Sadovoy.
According to Lvov mayor, UEFA inspector has pointed out to the lack of good administrative team for airport reconstruction.
Earlier it was mentioned that Lvov airport reconstruction is suspended because of delay in working drawings transfer to the general contractor.
We remind that on April, 9th reconstruction of take-off runway at Lvov International airport began.
Permalink Comments off