Stadium construction in Warsaw slows down as holidays approach
In Poland’s capital were halted noisy construction works in the National stadium for the period of Christmas and New Year holidays from December 23, 2008 up to January 5, 2009.
Works delay became possible thanks to advance in construction schedule, as informed in PL 2012 Company which coordinates preparation of Poland for hosting Euro-2012.
“That’s for our residents living next to the National stadium. Hammering in the piles may terribly disturb them” - told Janush Kublinsky, vice-President of the company for Construction Affairs.
According to PL 2012 data, at the moment 64% of the work with 48% scheduled is already carried out.